small CAMA logo
CAMA Gets a Corliss Steam Engine
Part 2 - Preparation of the Engine for Removal

The Lafayette Paper Nagle-Corliss engine sat 15 feet below the nearest parking area. The CAMA volunteer crew had to bring in electric power and compressed air to an area that was only accessible by ladder.  All tools had to be carried down the ladder or lowered by rope and pulley.  A hole in the wall nearest the generator and compressor was jackhammered so air and electric could be passed into the engine room.  Ray deZara carefully planned out the entire process of preparing the engine for removal. 

The basic steps to be carried out were as follows: 1) Clean out debris surrounding the engine to expose the engine and make for safe working conditions, 2) remove all small parts from the engine for separate packing, 3) disconnect the main and valve timing connecting rods, 4) disassemble inboard and outboard main bearings, 5) loosen bolts holding the flywheel halves together, 6) jack up the flywheel/crankshaft assembly to separate from the engine frame, and 7) release the engine frame from it's concrete and grout foundation.  

removing I beam    
  overhead debris
ABOVE:
Alot of overhead steel and iron debris had to be removed to clear the engine for removal.  This large I-beam was directly over the engine.  The beam was cut and let down to the floor using cables and pulleys.
ABOVE:
This pile of electrical conduit, wood and iron was just some of the overhead clutter removed. The I-beam at the 3 o'clock position in this photo is the same one pictured in the photo to the left.

  pit dig
  pit dig2
ABOVE:
All the debris in the flywheel pit had to be dug out by hand to reach a solid floor on which to build a cribbing pile. In this photo, much less than half of the coal ash and other junk has yet to been removed from the pit.
ABOVE:
In order to free the engine frame from its concrete and grout foundation, the weight of the flywheel and crankshaft had to be lifted off the frame. In order to lift the flywheel, cribbing had to be built up under it. This cribbing had to be on firm footing to hold the weight of the flywheel/crank assembly. In this photo, not all the debris is yet removed. 
small parts  
   flywheel bolts
ABOVE:
This photo shows some of the small parts (connecting rods, main bearing cap, etc) that have been removed from the engine.
ABOVE:
The bolts holding the flywheel halves together had to be loosened. The bolts on this side were particularly stubborn since they were buried under the coal ash in the pit. The flywheel had to be turned using a come-along until the halves of the flywheel were at top and bottom.
main bearing
taking shape
ABOVE:
A view of the inboard main bearing assembly after removal of the bearing cap.
ABOVE:
A view of the engine  as prep work procedes.
water in pit
cribbing
ABOVE:
Back down in the pit, water has begun to seep in but the concrete floor of the pit has been reached.
ABOVE:
Now, with a firm footing for the cribbing, a pile is built, centered under the flywheel.  To lift the flywheel, a 30 ton capacity airbag is used. The airbag is placed between the cribbing and the flywheel and inflated with compressed air. This lifts the flywheel about two inches, enough to insert wedges. The airbag is then deflated and the flywheel/crank assembly now rests on the cribbing pile, free of the engine frame.
crank up
frame up
ABOVE:
Another view of the inboard main bearing with the crankshaft now lifted clear of the engine frame.  All grout surrounding the engine frame is now jackhammered free to expose the base of the engine frame.
ABOVE:
Now, using a combination of mechanical and hydraulic jacks, the engine frame can be broken loose of the remaining grout and lifted free of the foundation. With the grout removed, the bolts that held down the engine frame can be torched.
whole frame loose
ready to go
ABOVE:
A good view of the engine frame sitting on wood blocking and free of the foundation.
ABOVE:
It was a dirty job, but with Ray's careful planning and the hard work of dedicated volunteers, the engine is now ready to be lifted out of the building.  All of the work described on this page was carried out in three weekends!

Thanks go out to the small crew that accomplished something to be proud of!
Thanks go out to Ray deZara, Jim Anderson, Jim Daly, Trevor Marshall, Pat Moran, and Todd Syska.


Click here to go to top of this page

Click here to go back to page 1 of the Nagle-Corliss story

Click here to go to page 3 of the Nagle-Corliss story

Click here to return to the Home Page

This page was created on 1/16/07 by Jim Anderson