small CAMA logo
INDUSTRIAL HALL EXPANSION
Progress as of 2/10/05

The Industrial Hall expansion started in the spring of 2004. Groundbreaking and foundation work was done in April.  Work was then put on hold while we looked for ways to fund further construction.  Two very generous donations (Dibner Foundation and the Diebold family) allowed us to continue construction after the Fall Festival. Current funding allows us to have a weathertight structure.  Further funding will be required to finish the interior, but notably, the C.H Brown engine is now protected from the elements. 

groundbreaking    
  pouring concrete
  ABOVE:
  On April 9, 2004, volunteers broke ground for the Industrial Hall Expansion.  Site preparation was carried out by CAMA members Jim Daly, Bob Hungerford, and  Jim  Robinson.

 ABOVE:
On April 12, 2004, footings were poured and on April 16, 2004 the foundation was poured.  Work was suspended on the expansion until after the Fall Festival. 

  framing begins
  flying in
ABOVE:
Following the Fall Festival, CAMA volunteers worked to build the four roof trusses shown in the background. Thanks to Jim Anderson, Dave Barrett, Jim Daly, Dick Greene, Bob Hungerford, Irene Jones, John Pawloski,  and Bob Pitcher for contributing to this construction.  In mid-Demember, Pine Ridge Pole Barns began framing (shown foreground).

ABOVE:
On 1/2/05, the Tom Laganga of DBL Crane Service arrived and assisted Pine Ridge in erecting the wall segments and the trusses. CAMA thanks Tom for  donating  his crane services.  The custom  cut lumber for the  job came from Moore's Sawmill.

framed  
purlins in place  
ABOVE:
At the end of the day on Jan. 2nd, we had something that looked more like a building and less like a pile of lumber. 

ABOVE:
After Jan. 2nd, the weather declined rapidly, and a series of snowstorms and cold blasts slowed work. Even with bad weather, by Jan. 15, the purlins were in place.

sided
CH brown
ABOVE:
Fast forward to 2/8/05 and look at the progress! The monitor is framed, sheathed and sided. The building is now weathertight. Work is now suspended until the windows arrive.
ABOVE:
The C.H. Brown steam engine now has a roof over it's head! Once the windows arrive and are installed, the original south wall of the Industrial Hall will be removed. The existing  doors and windows will be bumped out to the new south wall.

2/8/05 Industrial Hall
ABOVE:
The new and improved Industrial Hall as it appears on 2/8/05.  Since this photo was taken the expansion has been roofed. 

Thanks go to CAMA volunteers Jim Anderson, Dave Barrett, Chip Brown, Jim Daly, Vicky Daly, Ray deZara, Dick Greene, Bob Hungerford, Irene Jones, Tony Licursi, John Pawloski, Bob Pitcher, and Jim Robinson for their help in making the Industrial Hall expansion a reality.

Also, thanks go to DBL Crane Service (Tom Laganga), DG Concrete Construction, Lasco Roofing (George Bassette), Moore's Sawmill (Don Moore), Pine Ridge Pole Barns (Bob Sirchia, building contractor) and Sega Ready Mix.

Click here to go to the 3/6/06 Industrial Hall Expansion Update

Click here to go to the top of this page

Click here to return to the Home Page

This page was updated on 3/6/06 by Jim Anderson